Business Model


Approach

Atlantic Geothermal will demonstrate the viability of the non-fracturing, closed-loop energy mine by building a 160MW power plant in stages.

Phase I - Dept of Defense Technical Ready Level 7

        Location secured

        Detailed plan with all regulatory approvals

        Magnetic telemetry survey completed

        Equipment in place

Phase 2 - Working Pilot

        Staged drilling

        One lock

        5-10K foot depth

        100 foot horizontal shaft

        Abbreviated loop radiator

Phase 3 - Fully operational power plant

        Depth reaching 300-400° F ground temperature (~ 30,000 feet)

       Full 200 loop radiator

       160MW power generation

 

Funding

Phases 1 and 2 will be funded by a combination of angel/venture investment, university research grants and industry partnership investment. Phase 3 will be financed with a bond.  The exit strategy options are sale of the company, sale of the plant, licensing the technology.

Phase 1 - $3M (2 months)

        $300K   - Magnetic Telemetry Survey

        $500K   - Permitting

        $1M      - Labor & Professional Services

        $1.2M   - Equipment Deposit

Phase 2 - $38M (3 months)

        $4M      - One year land lease & cleanup insurance

        $12M    - Labor 

        $10M    - Equipment 90 Day Lease

        $12M    - Material & Supplies

Phase 3 - $760M (3 years)

        $12M    - Insurance

        $45M    - Labor

        $320M  - Equipment Purchase

        $238M  - Equipment Lease

        $145M  - Materials & Supplies


 

 